AIL India is investing 6 billion rupees ($63.1 million) to build a heating unit at its Ratnagiri LNG terminal to help it gasify the super-chilled fuel, the company’s business development director told reporters on Wednesday.
* The facility, due to be completed by June 2027, will enable the company to run the LNG terminal at its full capacity of 5 million tons per annum, R. K. Singhal said at an industry event.
* The facility is operating at about 50% capacity as the heating unit is not ready, Singhal said.
* The Ratnagiri facility was generating heat through the waste of a power plant operated by another entity to gasify the fuel. That plant is not functional now, he said.